Landscape Scope of Work

Landscape Scope of Work

Prepared by: [YOUR NAME]
Email: [YOUR EMAIL]
Company Name: [YOUR COMPANY NAME]
Company Number: [YOUR COMPANY NUMBER]
Company Address: [YOUR COMPANY ADDRESS]
Website: [YOUR COMPANY WEBSITE]
Social Media: [YOUR COMPANY SOCIAL MEDIA]


Introduction

This Landscape Scope of Work (SOW) document outlines the comprehensive plan for the residential landscaping project at 789 Elm Street, Springfield, IL 62704. The purpose of this SOW is to define the scope, deliverables, timeline, and responsibilities associated with the landscaping work to be carried out. This will ensure all parties involved have a clear understanding of the project objectives and expectations.


Scope of Work

Project Title: Residential Landscaping Enhancement
Client Name: Emma Johnson
Project Location: 789 Elm Street, Springfield, IL 62704

1. Project Objectives

  • Enhance the aesthetic appeal of the residential property.

  • Improve the functionality of outdoor spaces.

  • Ensure sustainability and low-maintenance features.

2. Scope of Work

The following tasks will be carried out:

  • Site Preparation: Clearing, grading, and soil preparation.

  • Planting: Selection and planting of trees, shrubs, flowers, and grass.

  • Hardscaping: Installation of pathways, patios, retaining walls, and other structures.

  • Irrigation System: Design and installation of an efficient irrigation system.

  • Lighting: Installation of outdoor lighting fixtures to enhance the landscape at night.

  • Maintenance: Initial maintenance and care instructions for newly installed plants and features.

3. Deliverables

  • Design Plans: Detailed drawings and plans for the landscaping design.

  • Material List: Comprehensive list of materials and plants to be used.

  • Project Report: A final report summarizing the completed work.

4. Timeline

The project will follow the schedule outlined below:

Task

Start Date

End Date

Duration

Status

Site Preparation

January 15, 2050

February 15, 2050

1 Month

Scheduled

Planting

February 16, 2050

March 31, 2050

1.5 Months

Planned

Hardscaping

April 1, 2050

May 15, 2050

1.5 Months

Planned

Irrigation System

May 16, 2050

June 15, 2050

1 Month

Planned

Lighting

June 16, 2050

June 30, 2050

2 Weeks

Planned

Maintenance & Final Review

July 1, 2050

July 15, 2050

2 Weeks

Planned

5. Responsibilities

  • [YOUR COMPANY NAME] will be responsible for executing all tasks as outlined.

  • Emma Johnson will provide access to the property and approve design plans.

  • Any additional costs or changes to the scope must be approved in writing by both parties.

6. Budget

The budget for the project will be determined based on the final design and material selections. A detailed cost estimate will be provided once the design plans are finalized.

7. Payment Terms

Payments will be made according to the following schedule:

  • Deposit: 30% upon acceptance of the SOW.

  • Progress Payment: 40% upon completion of planting.

  • Final Payment: 30% upon project completion and final review.

8. Contact Information

For any questions or additional information, please contact:

  • [YOUR NAME]

  • Email: [YOUR EMAIL]

  • Phone: [YOUR PHONE NUMBER]

Scope of Work Templates @ Template.net