Residential Construction Scope of Work

Residential Construction Scope of Work

Project Name: New Home Construction

Project Location: 578 Pinewood Avenue, San Francisco, CA 94116

Project Start Date: January 15, 2050

Estimated Completion Date: December 31, 2051

Contractor: [YOUR COMPANY NAME]

1. Site Preparation

  • Description: Clearing and grading of the site at 578 Pinewood Avenue, San Francisco, CA 94116 to prepare for the foundation.

  • Tasks:

    • Remove debris, vegetation, and existing structures as necessary.

    • Excavate the land to the required depth for the foundation.

    • Grade the land to ensure proper drainage and structural support.

  • Timeline: January 15, 2050 – February 28, 2050

  • Materials Required: Excavators, soil, gravel, backfill.

  • Responsible Party: Blue Sky Excavation, Inc. (Contact: Margaret Sanders)

2. Foundation

  • Description: Construction of a concrete slab foundation for a single-family home.

  • Tasks:

    • Pour concrete foundation according to blueprints.

    • Install necessary reinforcement such as rebar.

    • Allow curing period of 30 days before commencing framing work.

  • Timeline: March 1, 2050 – April 15, 2050

  • Materials Required: Concrete, rebar, moisture barriers.

  • Responsible Party: Premier Concrete Works (Contact: Stephen Connors)

3. Framing

  • Description: Erection of the home’s structural framing, including walls, floors, and roof trusses.

  • Tasks:

    • Construct the framework for the home’s structure.

    • Install floor joists, wall studs, and roof trusses per design specifications.

    • Coordinate with plumbers and electricians for rough-ins.

  • Timeline: April 16, 2050 – June 30, 2050

  • Materials Required: Lumber, nails, trusses, sheathing.

  • Responsible Party: [YOUR COMPANY NAME]

4. Roofing

  • Description: Installation of a weather-resistant roofing system.

  • Tasks:

    • Install roof decking, underlayment, and chosen roofing material (e.g., shingles or tiles).

    • Ensure proper ventilation and gutter systems.

  • Timeline: July 1, 2050 – August 15, 2050

  • Materials Required: Roof tiles/shingles, underlayment, flashing, gutters.

  • Responsible Party: Premier Concrete Works (Contact: Stephen Connors)

5. Plumbing and Electrical Rough-In

Task

Start Date

End Date

Materials Required

Responsible Party

Plumbing Rough-In

July 15, 2050

August 15, 2050

Pipes, fittings, valves

Flowline Plumbing, LLC (Contact: Linda Beckett)

Electrical Rough-In

July 15, 2050

August 30, 2050

Wires, outlets, breaker box

Swift Electric Solutions (Contact: Jacob Larson)

Inspection (Plumbing)

August 20, 2050

August 21, 2050

N/A

Local Inspector

Inspection (Electrical)

September 1, 2050

September 2, 2050

N/A

Local Inspector

Final Fixture Installation

December 1, 2051

December 10, 2051

Faucets, lighting fixtures

[YOUR COMPANY NAME]

6. Insulation and Drywall

  • Description: Insulation of walls, floors, and ceilings followed by drywall installation and finishing.

  • Tasks:

    • Install insulation throughout the home for thermal efficiency.

    • Hang, tape, and finish drywall.

  • Timeline: September 5, 2050 – November 15, 2050

  • Materials Required: Insulation (batts or spray foam), drywall sheets, joint compound.

  • Responsible Party: InsulPro Services (Contact: Emily Hayes)

7. Interior and Exterior Finishes

  • Description: Installation of interior and exterior finishes, including painting, flooring, cabinetry, and siding.

  • Tasks:

    • Paint interior and exterior walls.

    • Install flooring (e.g., hardwood, tile, carpet).

    • Fit cabinetry, countertops, and doors.

  • Timeline: November 20, 2050 – June 1, 2051

  • Materials Required: Paint, flooring, cabinets, doors, siding.

  • Responsible Party: [YOUR COMPANY NAME]

8. Final Inspections and Walkthrough

  • Description: Conduct final inspections to ensure the home meets all safety, code, and quality standards. A walkthrough will be completed with the homeowner.

  • Tasks:

    • Schedule inspections with local authorities.

    • Perform a final walkthrough with the client to address any concerns or punch-list items.

  • Timeline: December 1, 2051 – December 31, 2051

  • Responsible Party: [YOUR COMPANY NAME]

9. Project Completion

  • Description: Handover of keys and final documentation to the homeowner.

  • Tasks:

    • Provide all warranties, manuals, and final payment invoices.

    • Transfer ownership and completion documentation to the client.

  • Timeline: December 31, 2051

  • Responsible Party: [YOUR COMPANY NAME]


This document is intended to provide clear guidance on the expectations, deliverables, and timeline for the successful completion of the new home construction. If there are any changes to the SOW during the project, both parties must agree and sign an addendum to this agreement.

For any inquiries, please contact [YOUR NAME] at [YOUR EMAIL] or [YOUR COMPANY NUMBER].

Scope of Work Templates @ Template.net