Free Construction Project Weekly Report Template
Construction Project Weekly Report
Company: [Your Company Name]
Prepared by: [Your Name]
Report Period: [Date]
1. Executive Summary
The project continues to progress according to schedule with all major milestones being met. During the week, we achieved significant progress in the structural steelwork, electrical installation, and mechanical systems. No critical issues were encountered, and safety protocols remain at the highest standards. The project is on track for the completion target of July 2053.
2. Work Completed This Week
Activity |
Location |
Status |
Remarks |
---|---|---|---|
Structural Steel Erection |
Level 25 |
100% Complete |
Steel framework installation completed. |
HVAC Ductwork Installation |
Level 20 |
80% Complete |
Delayed by 1 day due to material delivery. |
Electrical Wiring |
Levels 10-15 |
100% Complete |
Inspections passed, ready for testing. |
Curtain Wall Installation |
East Elevation |
60% Complete |
Work proceeding as planned. |
Waterproofing |
Basement Level |
100% Complete |
No leaks detected, quality control cleared. |
3. Planned Work for Next Week
Activity |
Location |
Expected Start Date |
Expected Completion |
---|---|---|---|
Elevator Shaft Concrete Pour |
Core Area |
November 12, 2052 |
November 16, 2052 |
Plumbing Rough-In |
Levels 15-18 |
November 11, 2052 |
November 17, 2052 |
Glass Façade Installation |
West Elevation |
November 13, 2052 |
November 20, 2052 |
Drywall Installation |
Levels 5-8 |
November 14, 2052 |
November 21, 2052 |
Testing of Electrical Systems |
Level 10-15 |
November 15, 2052 |
November 18, 2052 |
4. Safety Report
-
Incidents: No major incidents reported this week.
-
Near Misses: 1 near-miss involving a worker while moving a steel beam. No injuries occurred, but additional safety briefings will be conducted.
-
Safety Training: Conducted PPE (Personal Protective Equipment) refresher training on November 7, 2052 for all workers.
5. Issues/Concerns
-
Material Delay: Delivery of HVAC ducting material was delayed by 1 day. The subcontractor has committed to working over the weekend to stay on track.
-
Weather Conditions: Mild rain on November 8, 2052, caused a brief slowdown of the façade installation. Contingency plans in place for possible future weather impacts.
-
Manpower: No manpower shortages; all trades are fully staffed.
6. Quality Control
-
Inspection: Electrical wiring and waterproofing passed inspection with no issues.
-
Testing: Electrical systems on levels 10-15 are scheduled for testing next week.
7. Schedule Update
The project remains on schedule with no critical path delays. Minor adjustments are being made to HVAC and façade installation timelines due to material and weather-related delays, but these do not affect the overall project completion date.
8. Financial Overview
-
Current Budget: $120 million
-
Expenses to Date: $72 million
-
Remaining Budget: $48 million
-
Change Orders: No new change orders this week.
9. Photos (Attached)
-
Structural steelwork completion at Level 25.
-
Waterproofing installation at the basement level.
-
Curtain wall progress on the east elevation.
10. Next Steps / Action Items
-
Monitor HVAC ductwork progress to ensure it meets the adjusted timeline.
-
Complete elevator shaft concrete pour.
-
Begin testing of electrical systems on lower floors.
-
Conduct safety audit for façade installation activities.