Construction Accomplishment Report

CONSTRUCTION ACCOMPLISHMENT REPORT

Reported by: [Your Name], Project Manager


Project Overview:

  • Project Name: Peoria Complex

  • Project Location: Peoria, AZ 85345

  • Start Date: January 15, 2050

  • Expected Completion Date: December 30, 2051

  • Scope of Work: Construction of 200 residential units, parking, and landscaping.


Accomplishments:

Task Completed

Date Completed

Excavation and foundation work for Building 1

October 15, 2050

Structural Framing for Building 1

November 5, 2050

Plumbing installation for Building 1

November 8, 2050

Site grading for parking area

November 10, 2050


Work in Progress:

Task In Progress

Expected Completion Date

Framing for Building 2

November 20, 2050

Electrical installation for Building 1

November 25, 2050

Excavation for parking lot 2

December 5, 2050


Issues or Delays:

Issue

Impact

Delay in steel beam delivery for Building 2

5-day delay in framing work

Rain delays for site grading

7-day delay in foundation work


Next Steps:

Task

Planned Date

Start electrical & HVAC installation for Building 2

December 1, 2050

Continue landscaping for Building 1

December 10, 2050

Start framing for Building 3

December 15, 2050


Conclusion:

The Peoria, AZ Complex is progressing well, with key tasks completed on schedule. A few minor delays have occurred, but they are being addressed, and the project remains on track. Future work will focus on the continued development of Building 2 and preparation for Building 3.