Construction Accomplishment Report
CONSTRUCTION ACCOMPLISHMENT REPORT
Reported by: [Your Name], Project Manager
Project Overview:
-
Project Name: Peoria Complex
-
Project Location: Peoria, AZ 85345
-
Start Date: January 15, 2050
-
Expected Completion Date: December 30, 2051
-
Scope of Work: Construction of 200 residential units, parking, and landscaping.
Accomplishments:
Task Completed |
Date Completed |
---|---|
Excavation and foundation work for Building 1 |
October 15, 2050 |
Structural Framing for Building 1 |
November 5, 2050 |
Plumbing installation for Building 1 |
November 8, 2050 |
Site grading for parking area |
November 10, 2050 |
Work in Progress:
Task In Progress |
Expected Completion Date |
---|---|
Framing for Building 2 |
November 20, 2050 |
Electrical installation for Building 1 |
November 25, 2050 |
Excavation for parking lot 2 |
December 5, 2050 |
Issues or Delays:
Issue |
Impact |
---|---|
Delay in steel beam delivery for Building 2 |
5-day delay in framing work |
Rain delays for site grading |
7-day delay in foundation work |
Next Steps:
Task |
Planned Date |
---|---|
Start electrical & HVAC installation for Building 2 |
December 1, 2050 |
Continue landscaping for Building 1 |
December 10, 2050 |
Start framing for Building 3 |
December 15, 2050 |
Conclusion:
The Peoria, AZ Complex is progressing well, with key tasks completed on schedule. A few minor delays have occurred, but they are being addressed, and the project remains on track. Future work will focus on the continued development of Building 2 and preparation for Building 3.