Prepared by: [Your Name]
Date: December 11, 2050
This schedule outlines the detailed breakdown of the values for the contract work to be completed. The sections below are provided to guide in tracking project progress and payments.
Item No. | Description | Unit Cost | Quantity | Total Cost |
---|---|---|---|---|
1 | Site Preparation | $10,000 | 1 | $10,000 |
2 | Foundation Work | $15,000 | 1 | $15,000 |
3 | Framing | $20,000 | 1 | $20,000 |
4 | Plumbing | $5,000 | 1 | $5,000 |
5 | Electrical | $7,000 | 1 | $7,000 |
6 | Roofing | $12,000 | 1 | $12,000 |
7 | Interior Finishes | $18,000 | 1 | $18,000 |
8 | Landscaping | $3,000 | 1 | $3,000 |
9 | Final Inspection | $2,000 | 1 | $2,000 |
All amounts are in USD.
Payments will be processed based on completed milestones.
Final payment will be due upon project completion.