Free Construction Job Costing Template

Construction Job Costing

This Construction Job Costing Report provides a detailed analysis of the financial performance for the City Center Tower project, a major construction initiative undertaken in Metropolis, USA. The report spans from the project’s commencement on January 1, 2050, through its completion on December 31, 2052.

Project Name: City Center Tower

Location: Metropolis, USA

Project Start Date: January 1, 2050

Project End Date: December 31, 2052

Cost Category

Description

Estimated Cost (USD)

Actual Cost (USD)

Variance (USD)

1. Labor Costs

1.1

Site Preparation

[2,500,000]

[2,600,000]

[+100,000]

1.2

Foundation Work

[4,000,000]

[3,950,000]

[-50,000]

1.3

Superstructure

[6,500,000]

[6,700,000]

[+200,000]

1.4

Electrical and Plumbing

[3,200,000]

[3,250,000]

[+50,000]

2. Material Costs

2.1

Concrete

[1,800,000]

[1,850,000]

[+50,000]

2.2

Steel

[2,000,000]

[1,950,000]

[-50,000]

2.3

Finishes and Fixtures

[1,500,000]

[1,600,000]

[+100,000]

3. Equipment Costs

3.1

Cranes and Lifts

[750,000]

[800,000]

[+50,000]

3.2

Tools and Machinery

[500,000]

[450,000]

[-50,000]

4. Overhead Costs

4.1

Project Management

[1,200,000]

[1,250,000]

[+50,000]

4.2

Administrative Expenses

[600,000]

[620,000]

[+20,000]

5. Contingency

[1,000,000]

[950,000]

[-50,000]

6. Total Costs

[25,150,000]

[25,500,000]

+[350,000]

Summary:

  • Total Estimated Cost: [25,150,000] USD

  • Total Actual Cost: [25,500,000] USD

  • Total Variance: [+350,000] USD

Notes:

  1. The project experienced a variance mainly due to increased labor and material costs.

  2. Contingency funds were not fully utilized, which somewhat mitigated the overall cost overrun.

  3. Several cost-saving measures were implemented, including bulk purchasing and efficient methods, but these were offset by unforeseen increases in certain areas.

Prepared by: [Your Name]