Free Architecture Construction Schedule Template

Download

Share

Free Architecture Construction Schedule Template

Architecture Construction Schedule

This construction schedule outlines the phases and tasks involved in the project, along with their respective timelines, providing a clear framework for managing the construction process effectively.

Project Name:

Location:

Project Manager:

Start Date:

Estimated Completion Date:

Phase

Task Description

Start Date

End Date

Duration (Days)

Pre-Construction

Site Analysis

Conduct site survey and soil testing

7

Design Development

Finalize architectural design

52

Permitting

Obtain necessary permits

29

Construction

Site Preparation

Clear and grade site

14

Foundation

Pour foundation

21

Framing

Construct building frame

40

Roofing

Install roof structure

15

Exterior Finishes

Apply exterior finishes and siding

20

Interior Work

Electrical & Plumbing

Install electrical and plumbing systems

30

HVAC Installation

Install HVAC systems

16

Insulation

Insulate walls and ceilings

10

Drywall Installation

Install and finish drywall

21

Interior Finishes

Paint, flooring, and interior trim

25

Final Steps

Final Inspections

Conduct final inspections

10

Punch List Completion

Address any remaining issues

10

Project Handover

Handover completed project to client

1

Notes:

  • The schedule is subject to change based on project progress and unforeseen circumstances.

  • Coordination meetings will be held weekly to review progress and address any issues.