Monthly Status Report Format

MONTHLY STATUS REPORT FORMAT

Project Title: [Insert Project Name]
Reporting Period: [Month, Year]
Report Prepared By: [Author Name]
Date: [Insert Date]


1. Executive Summary

  • Purpose: This report provides an overview of the project’s status, including progress against the schedule, budget adherence, key achievements, challenges, and action items for the upcoming month.

  • Overall Status: [On Track / At Risk / Off Track]

  • Budget Status: [On Budget / Over Budget / Under Budget]


2. Project Status Overview

Metric

Current Status

Target

Variance

Planned Start Date

[Insert Date]

[Insert Date]

[Insert Variance]

Planned End Date

[Insert Date]

[Insert Date]

[Insert Variance]

Current Phase

[Insert Phase]

[N/A]

[N/A]

% Completion

[Insert Percentage]

[Insert Percentage]

[Insert Variance]

2.1 Narrative Summary

  • The project is currently in the [Insert Phase] phase, with % Completion at [Insert Percentage].

  • The project is expected to meet the planned end date of [Insert Date], barring any unforeseen circumstances.


3. Key Milestones Achieved

Milestone

Target Date

Actual Date

Status

[Milestone 1]

[Insert Date]

[Insert Date]

[Achieved / Not Achieved]

[Milestone 2]

[Insert Date]

[Insert Date]

[Achieved / Not Achieved]

[Milestone 3]

[Insert Date]

[Insert Date]

[Achieved / Not Achieved]

3.1 Additional Achievements

  • [Detail any additional achievements not covered in the milestones table]

  • Examples:

    • [Achievement 1: Brief Description]

    • [Achievement 2: Brief Description]


4. Upcoming Milestones

Milestone

Planned Date

Responsible Party

Dependencies

[Milestone 1]

[Insert Date]

[Insert Name]

[Insert Dependencies]

[Milestone 2]

[Insert Date]

[Insert Name]

[Insert Dependencies]

[Milestone 3]

[Insert Date]

[Insert Name]

[Insert Dependencies]

4.1 Planned Activities

  • Activities for next month:

    • [Activity 1: Brief Description]

    • [Activity 2: Brief Description]


5. Budget Overview

Budget Item

Initial Budget

Current Expenditure

Variance

[Budget Item 1]

[Insert Amount]

[Insert Amount]

[Insert Variance]

[Budget Item 2]

[Insert Amount]

[Insert Amount]

[Insert Variance]

[Budget Item 3]

[Insert Amount]

[Insert Amount]

[Insert Variance]

5.1 Narrative Summary

  • Current Budget Status:

    • The project is currently [On Budget / Over Budget / Under Budget].

    • Major factors affecting the budget include:

      • [Factor 1: Brief Description]

      • [Factor 2: Brief Description]


6. Challenges/Risks

Challenge/Risk

Description

Impact Level

Mitigation Strategy

[Challenge/Risk 1]

[Description]

[High/Medium/Low]

[Mitigation Plan]

[Challenge/Risk 2]

[Description]

[High/Medium/Low]

[Mitigation Plan]

6.1 Additional Considerations

  • [Include any additional notes on challenges or risks that are relevant but not captured in the table.]


7. Action Items

Action Item

Responsible Party

Due Date

Status

[Action Item 1]

[Insert Name]

[Insert Date]

[Open/Closed]

[Action Item 2]

[Insert Name]

[Insert Date]

[Open/Closed]


8. Conclusion

  • The project is [provide a summary of the overall status, challenges, and outlook for the upcoming period].

  • Next steps will include focusing on [insert focus areas], ensuring the project remains on track and within budget.


Attachments:

  • [Insert any supporting documents or appendices]

Prepared by:
[Author Name]
[Position]
[Contact Information]

Report Templates @ Template.net