Free Monthly Status Report Format Template
MONTHLY STATUS REPORT FORMAT
Project Title: [Insert Project Name]
Reporting Period: [Month, Year]
Report Prepared By: [Author Name]
Date: [Insert Date]
1. Executive Summary
-
Purpose: This report provides an overview of the project’s status, including progress against the schedule, budget adherence, key achievements, challenges, and action items for the upcoming month.
-
Overall Status: [On Track / At Risk / Off Track]
-
Budget Status: [On Budget / Over Budget / Under Budget]
2. Project Status Overview
Metric |
Current Status |
Target |
Variance |
---|---|---|---|
Planned Start Date |
[Insert Date] |
[Insert Date] |
[Insert Variance] |
Planned End Date |
[Insert Date] |
[Insert Date] |
[Insert Variance] |
Current Phase |
[Insert Phase] |
[N/A] |
[N/A] |
% Completion |
[Insert Percentage] |
[Insert Percentage] |
[Insert Variance] |
2.1 Narrative Summary
-
The project is currently in the [Insert Phase] phase, with % Completion at [Insert Percentage].
-
The project is expected to meet the planned end date of [Insert Date], barring any unforeseen circumstances.
3. Key Milestones Achieved
Milestone |
Target Date |
Actual Date |
Status |
---|---|---|---|
[Milestone 1] |
[Insert Date] |
[Insert Date] |
[Achieved / Not Achieved] |
[Milestone 2] |
[Insert Date] |
[Insert Date] |
[Achieved / Not Achieved] |
[Milestone 3] |
[Insert Date] |
[Insert Date] |
[Achieved / Not Achieved] |
3.1 Additional Achievements
-
[Detail any additional achievements not covered in the milestones table]
-
Examples:
-
[Achievement 1: Brief Description]
-
[Achievement 2: Brief Description]
-
4. Upcoming Milestones
Milestone |
Planned Date |
Responsible Party |
Dependencies |
---|---|---|---|
[Milestone 1] |
[Insert Date] |
[Insert Name] |
[Insert Dependencies] |
[Milestone 2] |
[Insert Date] |
[Insert Name] |
[Insert Dependencies] |
[Milestone 3] |
[Insert Date] |
[Insert Name] |
[Insert Dependencies] |
4.1 Planned Activities
-
Activities for next month:
-
[Activity 1: Brief Description]
-
[Activity 2: Brief Description]
-
5. Budget Overview
Budget Item |
Initial Budget |
Current Expenditure |
Variance |
---|---|---|---|
[Budget Item 1] |
[Insert Amount] |
[Insert Amount] |
[Insert Variance] |
[Budget Item 2] |
[Insert Amount] |
[Insert Amount] |
[Insert Variance] |
[Budget Item 3] |
[Insert Amount] |
[Insert Amount] |
[Insert Variance] |
5.1 Narrative Summary
-
Current Budget Status:
-
The project is currently [On Budget / Over Budget / Under Budget].
-
Major factors affecting the budget include:
-
[Factor 1: Brief Description]
-
[Factor 2: Brief Description]
-
-
6. Challenges/Risks
Challenge/Risk |
Description |
Impact Level |
Mitigation Strategy |
---|---|---|---|
[Challenge/Risk 1] |
[Description] |
[High/Medium/Low] |
[Mitigation Plan] |
[Challenge/Risk 2] |
[Description] |
[High/Medium/Low] |
[Mitigation Plan] |
6.1 Additional Considerations
-
[Include any additional notes on challenges or risks that are relevant but not captured in the table.]
7. Action Items
Action Item |
Responsible Party |
Due Date |
Status |
---|---|---|---|
[Action Item 1] |
[Insert Name] |
[Insert Date] |
[Open/Closed] |
[Action Item 2] |
[Insert Name] |
[Insert Date] |
[Open/Closed] |
8. Conclusion
-
The project is [provide a summary of the overall status, challenges, and outlook for the upcoming period].
-
Next steps will include focusing on [insert focus areas], ensuring the project remains on track and within budget.
Attachments:
-
[Insert any supporting documents or appendices]
Prepared by:
[Author Name]
[Position]
[Contact Information]