Free Residential Construction Report Template

Residential Construction Report

Prepared by: [Your Name]


I. Project Overview

The residential construction project at 123 Main Street is a two-story, single-family home designed with modern architecture. The project began on April 1, 2050, and its estimated completion date was initially scheduled for March 31, 2051.


II. Timeline Updates

A. Current Status

As of this month, the construction is progressing on schedule. The foundation and framing stages have been completed, and work on the roofing and exterior is underway.

B. Milestone Achievements

  • The foundation was completed on May 15, 2050

  • The framing was completed on July 10, 2050

  • Initial roofing was installed on September 5, 2050


III. Budget Adherence

A. Budget Overview

The total budget for this residential construction project is $500,000. As of the latest financial assessment, expenditures are on track, with careful monitoring to remain within budgetary constraints.

Category

Budgeted Amount

Spent Amount

Variance

Foundation

$80,000

$78,000

$2,000

Framing

$100,000

$102,000

-$2,000

Roofing

$50,000

$48,500

$1,500


IV. Inspections

A. Recent Inspections

The following inspections have been conducted in the past month:

  • Foundation integrity inspection - passed

  • Framing quality inspection - passed with notes for minor corrections

  • Roofing installation inspection - scheduled for November 10, 2050

B. Upcoming Inspections

Future inspections are scheduled according to the timeline of construction activities:

  • Plumbing rough-in inspection - December 1, 2050

  • Electrical rough-in inspection - December 15, 2050


V. Issues and Resolutions

A. Current Issues

No major issues are reported at this time. Only minor adjustments are needed for the framed walls to ensure full compliance with the project specifications.

B. Resolved Issues

Roofing materials were delayed by one week due to supply chain issues but have now been resolved and materials are on site.


VI. Changes or Delays

As mentioned earlier, the project encountered a brief delay in roofing materials, but this has been resolved without impacting the overall project timeline. No other changes or delays have been reported.